Site Update 17.01.2017

Bulk excavation works resumed after the New Year holiday and 38% of the reduced level excavation is now complete, representing 225 truckloads of material removed from site.  To prevent soiling of Mill Road surfaces an operator cleans all truck tyres before they leave the site, and a programme of road sweeping is under way. A piling rig will return to the site in late February to begin the secondary piling works. No accidents or complaints have been received to date, and noise monitoring is ongoing.

 